Even the best block loses its performance if it is laid wrongly. This page is written for the person laying it, not for the archive.

Laying a ceramic wall, stage by stage

  1. 01

    Prepare the bed

    The surface under the first course must be clean, level and free of dust. Check the first course with a straightedge and a laser level; an error here is amplified up the height of the wall.

  2. 02

    The right mortar

    A 1:5 sand–cement mortar or a ready-mixed masonry mortar. It should be workable but not sloppy. Consumption for each product is on its datasheet.

  3. 03

    Damp the block

    Damp on the surface, not soaked. A dry block draws the water out of the mortar; a wet one destroys adhesion.

  4. 04

    Coursing

    A full, even bed joint. With tongue-and-groove the perpend joint disappears. Check plumb and level every third course.

  5. 05

    Lintels

    No opening is built without a lintel. A ceramic lintel acts as permanent formwork and keeps the thermal continuity of the facade.

  6. 06

    Tying into the frame

    An infill wall must be restrained to the frame with posts and ties per the seismic requirements. This is the stage inspections pick up most often.

  7. 07

    Chasing for services

    Vertical chases are allowed. A horizontal chase must not exceed one third of the wall thickness and must be cut with a disc, not knocked out.

  8. 08

    Finishing

    Give the wall at least forty-eight hours before plastering. The block’s grooved face provides the key for the render.

What installers ask most

بله، اما فقط مرطوب — نه اشباع. مرطوب‌کردن سطحی مانع از آن می‌شود که بلوک آب ملات را بمکد. بلوک اشباع، برعکس، چسبندگی ملات را از بین می‌برد.

شیار قائم مجاز است، اما شیار افقی عمیق مقاومت دیوار را به‌شدت کاهش می‌دهد. حداکثر عمق شیار افقی نباید از یک‌سوم ضخامت دیوار بیشتر شود و باید از ابزار برش دیسکی استفاده شود، نه ضربه.

ملات ماسه‌سیمان با نسبت ۱:۵ یا ملات آماده‌ی بنایی. مصرف ملات هر محصول در دیتاشیت آن بر حسب لیتر بر متر مربع درج شده است.

حدود یک و نیم متر. اجرای بیش از این در یک نوبت، به‌دلیل وزن رگ‌های بالایی روی ملات تازه، می‌تواند به فشردگی درز و انحراف شاقولی منجر شود.